Platteville School District officials have selected an architectural firm to assist in a multimillion-dollar effort to update school infrastructure. The district is finalizing a contract with Plunkett Raysich Architects of Madison for design services and oversight of a possible bond measure that would appear before voters in November. Proposed improvements to Platteville High School include a community workout facility and walking track, a 13,500-square-foot gymnasium, new auditorium entryways, and kitchen and cold-storage renovations. To the north of the building, a new athletic field and track would be constructed. Additional bathrooms and three classrooms would be constructed at Platteville Middle School, while a new pickup and drop-off area would be added outside Westview Elementary School. At Neal Wilkins Early Learning Center, the student cafeteria would be remodeled and a 7,400-square-foot gymnasium constructed.