Construction continues on Platteville’s new fire facility. Despite minor delays due to recent rainfall, sitework remains on schedule. Utility lines and storm sewer systems are currently being finalized, with driveway and parking lot base infill expected to proceed once ground conditions permit. According to Platteville’s city website footing and foundation construction is anticipated to begin by early July.