Crews were set to begin demolishing a portion of the Dubuque Brewing and Malting Co. building this week, but that work has been delayed. Alliant Energy was prevented from removing overhead power lines until an electrical contractor completed the relocation of internal electric service that serves Prairie Farms, according to City Council documents. With that work completed, Alliant has scheduled the removal of the power lines for the week of March 25. No demolition can begin until the power lines are removed. Once begun, demolition is scheduled to last about three weeks. Cleanup of the site could take another week. The area set to be demolished includes sections of the building south of its archway entrance on Jackson Street.
Another delay in demotion of Dubuque building
Mar 19, 2024 | 11:36 AM
Latest Posts


Overnight storm damage in SW Wisconsin
Jun 18, 2026

Obituaries for Wednesday, June 17, 2026
Jun 17, 2026

AG Kaul joins lawsuit to protect voter rolls
Jun 17, 2026
Podcasts

Karl Klopotic's Final Forecast on WGLR 10-13-23
Oct 13, 2023
WGLR "Riders In The Sky" Interview With Ranger Doug
Oct 14, 2022
WBA Award for Excellence - Best Interview
Apr 26, 2022








